Method Statement -Installation of Wireless Telephone System
1.0
|
OBJECTIVE
| ||||||||
To outline the method statement for Wireless Telephone Installation (IP base PABX system)
| |||||||||
2.0
|
SCOPE
| ||||||||
To supply, install, programming an IP base PABX system ready type c/w built-in UPS for back-up upon
| |||||||||
failure up to 4 hours, voltage stabilizer, over voltage surge arrestor, with expandable to 500 ports
| |||||||||
extension and all necessary accessories, as per drawing and specification.
| |||||||||
3.0
|
REFERENCE
| ||||||||
· Project Specification.
| |||||||||
· Carrying out Construction / Installation works procedure inspection and test plan, inspection check list, etc.
| |||||||||
· Proposal drawing from specialist.
| |||||||||
4.0
|
RESPONSIBILITIES
| ||||||||
· Engineer
| |||||||||
· Supervisor
| |||||||||
5.0
|
MATERIALS
| ||||||||
· NEC SV8100 Series Business Features (Primary)
· NEC SV8100 Series Business Features (Secondary)
· Terminal (Operator)
· Terminal (Office Staff)
· OCS System
| |||||||||
6.0
|
HANDLING AND STORAGE OF MATERIALS
| ||||||||
Handling:
|
All materials received at site shall be checked according to the Delivery Order (D.O) and Purchase Order to ensure the materials received are in conformance.
| ||||||||
Storage:
|
Deliver the products to the protected area and stack / arrange the materials in a flat and dry surface place.
| ||||||||
7.0
|
PLANT, MACHINERY, EQUIPMENT AND TOOLS
| ||||||||
a.
|
Safety gears
| ||||||||
b.
|
Transportation i.e. Van, pickup truck
| ||||||||
c.
|
Basic hand tools (Needle nose pliers, wire stripper, network interface wire junction etc.)
| ||||||||
d.
|
Scaffolding
| ||||||||
8.0
|
PREPARATORY WORKS
| ||||||||
8.1
|
All installation works is according to the approved shop drawing and technical specification.
| ||||||||
8.2
|
Any deviation at site from the approved shop drawings shall seek the confirmation and clarification from
| ||||||||
Consultant or reported to Employer's Representative for approval on new proposal.
| |||||||||
9.0
|
WORK METHODOLOGY PROCEDURES
| ||||||||
9.1
|
General construction and installation of wireless telephone system.
| ||||||||
9.1.1
|
Site clearance.
| ||||||||
9.1.2
|
Documentation and drawing plan
| ||||||||
Prepare and submit to Consultant the presentation and approved by Consultant.
| |||||||||
9.1.3
|
Deliver of materials on site
| ||||||||
9.1.4
|
Checking of parts and materials on site
| ||||||||
9.1.5
|
Pre-requirement of installation
| ||||||||
M&E installation (such as of cable and trunking) being completed and Main Contractor is to ensure that the
| |||||||||
room is free from construction debris.
| |||||||||
9.1.6
|
Installation of wireless telephone system/Main PABX
| ||||||||
a.
|
Location of server and modem is determined at the management office.
| ||||||||
b.
|
Ensure the wireless system component part and etc. as per submitted of functional system shop drawings.
| ||||||||
c.
|
All cable termination into such as incoming and outgoing cable is terminated by insertion tool.
| ||||||||
d.
|
Programming of PABX system
| ||||||||
9.1.7
|
Installation and checking of grounding and surge protectors
| ||||||||
9.1.8
|
Installation and testing of the PABX to end user(wireless mode)
| ||||||||
9.1.9
|
Prepare documentation and user training
| ||||||||
10.0
|
TESTING PROCEDURES
| ||||||||
Testing , commissioning and configuration the following systems and guarantee full functionality of the
| |||||||||
system during defect and liability period as per scope of works & according to the requirements
| |||||||||
and specifications of ECER. (Contractor need to carry out pre-T&C for all the systems and submit the
| |||||||||
test results to ECER before T&C with ECER.
| |||||||||
· Check the system batteries and connection of cables.
· Check the polarity of batteries cables and ensure color code for positive and negative.
· Check the installation between the batteries back up and PABX.
· Measure the line voltage to the charger and ensure that the voltage is 220v with maximum of 5% up or down.
· Ensure the approval and acceptance of the telephone numbering plan by the Consultant.
· Upon completion of the above the PABX agent will start up the PABX and start the start up check of all the boards and hardware.
· Programming of the PABX will start according to the approved numbering plan, telephone numbers not to be changed to avoid destroying the PABX program.
| |||||||||
11.0
|
SAFETY FEATURES
| ||||||||
All operation during this work will be done in an efficient and safe manner and in accordance to the Safety
| |||||||||
procedures. However, there are issues concerning safety for this work that are to be observed base on the
| |||||||||
results of the audit, relevant safety measures will be proposed and implemented.
| |||||||||
a.
|
Carry out a Hazard Identification Audit (HIA) before start of work each day and before the start of new task.
| ||||||||
b.
|
The material shall be in good condition, clean and free from defect and crack during the installation.
| ||||||||
c.
|
All material shall be transported by lorry to the site. Upon arrival, the materials shall be unloaded at our
| ||||||||
storage yard, either manually or by machinery. All material shall be check and inspected by the Supervisor
| |||||||||
and Consultant. The materials are carefully stacked on timber and cover with non-staining plastic sheet.
| |||||||||
12.0
|
VERIFICATION CHECK LIST
| ||||||||
Based on proposal drawing.
| |||||||||
13.0
|
RECORDING
| ||||||||
Request for inspection form (as per attachment form)
| |||||||||